Colocado por: riscosgosto, vai levar um ensoleiramento com 30cm?
Colocado por: smpvfO steel esta atrasado (uns dias), mas parece que para a proxima semana vai comecar um pouco mais a serio.
Deixo aqui a data prevista para a execucao de alguns trabalhos.
Sera que vao cumprir?
· Wednesday the 26th the Structural Steel is delivered to site and the two legs for the exposed truss will be set up in the slab.
· Thursday the 27the the floor will be poured (Weather Dependant)
· Once the slab has been placed the floor will sit for a week to cure prior to the first stage of floor polishing.
· The first stage of Floor Polishing is scheduled for the 4th or 5th of May
· EMS are looking at installing the Septic and Water tanks around the 4th and 5th of May
· Level 1 frames are booked for delivery on the 8th of May
· Level 2 frames are booked for the 12th of May
· Trusses are booked for the 17th of May